Cross Laminated Timber: TTF Engineered Timber Forum Series

The Timber Trade Federation hosted the second seminar in its Engineered Timber Forum Series : Cross Laminated Timber, here at The Building Centre, on Thursday last week.

Always eager to enrich my knowledge of current thinking and trends in materials and methods of construction I was very pleased to be able to attend this event.

There was a wealth of expertise taking to the podium,that morning, representing Research and Development, Manufacturers, Architects, Engineers and Contractors.

Wayne Probert of Stora Enso Solutions gave a manufacturer’s view of CLT stressing the need to standardise board sizes. He said that Stora Enso was trying to lead the standardisation and explained the three basic board qualities available , Non Visual, Visual and Industrial Visual.

Wayne mentioned the other four largest global producers of CLT, Binderholz, KLH, Kaufmann and Metsä Wood all of which were represented at the seminar.

CLT-Bridport-House

Bridport House, Hackney

He introduced a short film about Bridport House, a successful social housing project in Hackney which was built using CLT. The frame for this eight storey building was put up in eight weeks and the build cost was £1470 per m2 .

The feed back from residents was very favourable. One lady said how she now paid much less for her heating than she did in her previous home and loved the amount of storage provided. A male resident was very impressed with the spaciousness of his  one bedroomed accommodation and there was unanimous approval of the large family balconies giving an unusual amount of private outside space to each unit.

Bridport House was also flagged up in Stefan Mannerwitz’s presentation for Karakusevic Carson Architects who designed the building. He told us of the difficulties in designing foundations to bridge a Victorian sewer and showed design details of the junction on the 1st to 4th floor and party wall.

Next, Frank Wering of Metsä Wood gave us some background to the development of their company, explaining that the wood for CLT comes from the forests of Finland. In 1990 the possibility of producing CLT was first explored and now large panels 4.8 metres by 20 metres are being manufactured. The panels are finger jointed and cross bonded. Air pressure is applied to strengthen the panels. Curved shapes are also possible and we were shown examples of projects where curved panels have been used.

We were shown some projects where hybrid timber products had been used including examples where their ’Kerto’ product was used inside their ‘Leno’ product to take advantage of the different products characteristics; Kerto’s being its long span and high load capabilities.

Tower of Love Pavillion Blackpool

Tower of Love Pavillion Blackpool

Jonas Lencer from dRMM Architects gave a case study of the Tower Festival Pavillion in Blackpool built in 2006 using CLT panels. Customised panels were used and clad externally with gold coloured stainless steel shingles and lignacite blocks which contained 30% recycled glass. The building is a popular wedding venue as a large 3metre by 6metre window affords an excellent view of Blackpool Tower as a backdrop for a wedding photo and on the other side of the building another window has views across the Irish sea.

Nic Clark spoke about KLH UK and Ramboll’s collaborative work which included two Academys in Norwich and one primary school. He emphasized the importance of stressing the benefits of building with CLT, to client and contractor: its carbon absorption properties, Breeam acceditation and CLT renewable credentials. In order to be able to stand shoulder to shoulder with other building methods and materials, the benefits have to be explained to the main contractors. With regard to savings, factory precision cuts for services can reduce the amount of on site fireproofing required for apertures. The captured savings can be passed back up the line to make more cost effective proposals.

Gavin White of Ramboll engineers continued the theme of the cost savings and the attributes of building with CLT but said that most Quantity Surveyors don’t understand how to price a timber building and therefore more education is required. A wrong calculation couild result in CLT not being the preferred option for the project.

He also suggested that timber options could be made more attractive and affordable by using hybrid building methods which could incorporate a steel building frame.
Matthew Linegar Technical Director of engineering company TimberFirst has worked with CLT for over seven years and has worked on over sixty CLT projects in the UK. He talked of designing to reduce wastage and therefore make cost savings. He championed the use of standard sized panels and using elements more efficiently.

Nick Milestone, Managing Director of B & K Structures and Helmut Spiehs of Binderholz gave examples of UK and European projects built with CLT. Examples of projects using off-site factory built, prefabricated panels showed how quickly projects could be completed. For example a seven storey appartment block in Germany was completed in four months.

CLT-Panel-Q&A's

CLT Panel Q&As

Jonathan Fovargue of in-house specialist timber engineers Eurban was the last speaker and traced the fast growth of the CLT market over the last ten years. The ten strong panel took questions at the end of the session.

It was good to be part of such a well attended event and hear from such a diverse cross section of diciplines from the construction industry. The over-riding thought that I took away from this very informative morning was that with this fast emerging market, continuing innovation would be the key to the industry’s continued growth and survival.